…Targets Quality Electricity Supply to Households
UYO
The Akwa Ibom State Government has unveiled a comprehensive package of financial, institutional and technical interventions to rescue the state’s electricity sector from years of operational difficulties, reposition Ibom Power Company and expand access to reliable electricity across the 31 local government areas.
At the centre of the intervention is a restructuring of Ibom Power Company Limited, which the government says inherited a $9 million debt obligation to the African Export-Import Bank (Afreximbank), alongside serious technical challenges, poor revenue recovery and inadequate capacity to sustain commercial operations.
To address the financial burden and prevent the loss of critical state-owned assets, the government has commenced servicing the inherited debt through quarterly payments of $500,000, while pursuing a private-sector concession arrangement to attract the technical expertise and investment required to rehabilitate and expand the power plant.
These disclosures were made during the 13th edition of the Ministerial Briefing and Media Interactive Session in Uyo, where the Commissioner for Power, Hon. Iniobong Robson, and the Commissioner for Information, Dr. Aniekan Umanah, provided updates on the government’s electricity sector reforms, the condition of Ibom Power, persistent low voltage and the transition towards an independent state electricity market.
The briefing provided insight into the administration’s efforts to address the structural problems confronting the electricity sector, including inherited financial obligations, ageing infrastructure, inadequate power generation and the limitations of the existing distribution network.
Providing details of the inherited financial burden, the Commissioner for Information, Dr. Aniekan Umanah, disclosed that the present administration inherited a $9 million debt obligation involving Afreximbank, which had placed Ibom Power’s financial stability and the state’s investment at considerable risk.
He explained that Governor Umo Eno intervened through a debt-restructuring arrangement, under which the state government now pays $500,000 quarterly towards servicing the obligation.
The intervention, according to him, is designed to protect the state’s investment and prevent the financial liabilities from undermining the future of the power company.
Beyond the debt burden, the Commissioner for Power, Iniobong Robson, explained that Ibom Power was established as a commercial enterprise expected to generate revenue, meet its operational costs and pay its workers without depending entirely on government subventions.
He disclosed that the facility was originally designed with three turbines, T1, T2 and T3, but T1 suffered a major breakdown within its first two years of operation. Consequently, only the 50-megawatt T3 turbine is currently operational.
The situation has been compounded by poor revenue recovery, with the company collecting less than 30 per cent of invoices for electricity supplied. The revenue generated, he explained, is insufficient to meet basic operational obligations, particularly gas supply costs.
Addressing concerns over workers’ unpaid salaries, Robson clarified that the more than 120 employees of Ibom Power are staff of a commercial enterprise and not civil servants adding that the company’s financial difficulties have affected its ability to sustain operations and meet its obligations.
To reverse the situation, the government is pursuing a private-sector concession arrangement covering Ibom Power and its proposed electricity distribution investment.
The Commissioner said proposals from prospective private-sector partners were being evaluated, adding that the objective was to attract investors capable of financing the rehabilitation, operation, maintenance and expansion of the facilities.
He emphasised that the proposed arrangement does not amount to the sale of Ibom Power or the surrender of the state’s ownership interests. Rather, it is intended to bring in private capital and technical expertise while government retains its underlying investments.
The government is also working to secure firm and sustainable long-term gas supply to guarantee consistent electricity generation.
Beyond rescuing Ibom Power, the administration is implementing a broader electricity sector reform programme intended to give Akwa Ibom greater regulatory control over electricity operations within its territory and create an investment framework capable of supporting improved service delivery.
The Commissioner recalled that Governor Eno convened the Akwa Ibom Electricity Summit in Ikot Ekpene on September 18 and 19, 2025, where the state’s electricity policy and law were unveiled and the reform programme formally adopted.
At the summit, the Governor outlined commitments to rehabilitate and commercialise Ibom Power, establish a state electricity distribution company with government equity participation, license electricity operators and ensure that every household in Akwa Ibom enjoys quality electricity service by 2034.
The reform programme is anchored on three major instruments: the Electricity Act 2023, as amended; the Akwa Ibom State Electricity Policy; and the Akwa Ibom State Electricity Law 2025.
To drive implementation, Governor Eno constituted a seven-member implementation committee in April 2026, chaired by his then Executive Assistant and Chief Delivery Adviser, Mr. Aniefiok Johnson.
The state has also incorporated Ibom Electricity Holdings Limited (IEHL) as the umbrella company to manage government investments across the electricity value chain.
The holding company is expected to oversee strategic investments in Ibom Power Company, Fourth Power Consulting Limited and the proposed state electricity distribution subsidiary to be carved out of the Port Harcourt Electricity Distribution Company (PHED).
Robson stressed that the government had neither sold nor intended to divest its interests in Ibom Power or relinquish its equity rights in the other electricity investments.
Another major component of the reforms is the establishment of the Akwa Ibom State Electricity Regulatory Commission (AKSERC), which is expected to provide the regulatory framework for an independent electricity market.
Governor Eno inaugurated the commission’s pioneer five-member board on June 4, 2026, following its screening and confirmation by the State House of Assembly. The commission is chaired by Mrs. Arit-Okon Uya.
A significant milestone in the reform process came on August 18, 2026, when the Nigerian Electricity Regulatory Commission (NERC) issued Order No. NERC/2026/087, transferring regulatory oversight of the state’s intrastate electricity market to AKSERC.
With the development, Akwa Ibom became the 17th state to receive such a regulatory transfer order.
Under the order, PHED is required to incorporate a subsidiary to assume responsibility for electricity supply and distribution within Akwa Ibom and obtain the necessary operating licence from AKSERC. The transition is expected to be completed by February 17, 2027.
The Commissioner said the state government had engaged the PHED board to ensure cooperation and a smooth transition that would protect the state’s commercial interests.
He added that the Ministry of Power, AKSERC and Ibom Electricity Holdings Limited would work with PHED, the Bureau of Public Enterprises and other relevant stakeholders to conclude the corporate, asset, liability and staff arrangements required for the transition.
Importantly, the government assured electricity consumers that the regulatory transition would not result in an immediate disruption of electricity supply, metering, billing or customer care.
PHED will continue to handle electricity distribution and customer services during the transition until the necessary arrangements are completed. The transfer of regulatory oversight does not automatically translate into an immediate change in electricity tariffs or service providers.
While the institutional reforms are being pursued, the government is also responding to complaints about low voltage, damaged transformers, leaning electricity poles and inadequate distribution infrastructure across communities.
Robson clarified that electricity distribution assets, including transformers, distribution lines and related facilities, fall within the statutory responsibility of PHED.
However, he disclosed that the state government had awarded a comprehensive contract for an assessment of the condition, age and operational lifespan of transformers across the 31 local government areas.
The assessment is expected to provide reliable data on transformers requiring repairs or replacement and guide the government’s intervention in collaboration with PHED.
The government is also working towards the establishment of the Akwa Ibom State Electrification Agency under Section 47 of the 2025 Electricity Law.
The organisational structure and operational framework of the agency have been completed and submitted to the Governor for approval.
The agency is expected to coordinate electricity access for underserved towns, villages and communities, particularly those without adequate connection to the national grid.
In addition, the Commissioner announced plans for a solar home system programme targeting households and small businesses in communities experiencing poor or unreliable grid electricity.
The initiative will be complemented by the training of Akwa Ibom youths in solar installation, operation and maintenance, creating opportunities for local participation in the emerging renewable energy sector.
On the implementation timeline, Robson said the state expected the incorporation of the Akwa Ibom electricity distribution subsidiary before the end of the fourth quarter of 2026.
AKSERC is also expected to commence publication of its initial regulatory instruments covering engineering codes, licensing procedures, customer care frameworks and tariff methodology.
The procurement process for Ibom Power and the proposed state distribution utility is expected to be concluded between the fourth quarter of 2026 and the first quarter of 2027, while the State Electrification Agency is also expected to become operational within the period.
Speaking on the regulatory framework, the Chairman and Chief Executive of AKSERC, Mrs. Arit-Okon Uya, assured prospective investors and electricity operators of a fair, transparent and standardised regulatory environment.
She explained that the commission was working to establish a viable and financially sustainable electricity market capable of attracting investments into the state.
According to her, AKSERC’s responsibility includes ensuring that operators across the electricity value chain, particularly those involved in generation and distribution, conduct their businesses in accordance with established regulatory standards.
She said the commission was developing the necessary regulatory instruments to guide operations, promote accountability and protect the interests of electricity consumers.
Uya expressed optimism that the state’s electricity resources and investment opportunities could position Akwa Ibom as a major electricity hub in Nigeria.
Robson, however, cautioned against expectations of an immediate transformation in electricity supply, explaining that rebuilding a sector affected by years of inadequate infrastructure required time, investment and technical expertise.
He also identified vandalism of transformers, electricity poles and power lines as major challenges, urging residents to protect public electricity infrastructure and report suspicious activities to the appropriate authorities.